Morgan Sindall

December 10, 2019

6000m of Kerbing Laid as Junction 29 M8 at Bishopton Opens to Public

The new Bishopton Interchange at Junction 29 of the M8 near Glasgow has opened to the public at midnight Wed 5th Dec 2019. CPR were contracted by Morgan Sindall to lay over 6000m of kerbing and block paving at the new road.
July 30, 2019

Aerial View of Kerbing Works at Bishopton Interchange (M8)

April 30, 2019

CPR Awarded Kerbing Contract for Bishopton Interchange

Morgan Sindall have contracted CPR to deliver kerbing works at the new construction site at Bishopton Interchange at Junction 29A of the M8 slip road to the Erskine Bridge.
November 1, 2017

Excavation, Ducting & Surfacing at Larbert Station

November 1, 2017

Progress Update for Millerhill Electric Train Depot

August 24, 2017

Deep Excavation During Final Stages of Millerhill Depot Construction

CPR are now entering the final stages of the deep excavation works at Millerhill Depot in our role as road construction contractor at the EGIP site n behalf of Morgan Sindall. We recently completed the deep excavation and installation of a separation tank on the site and are now excavating a suds pond.
August 1, 2017

Excavation & Deep Drainage at Road Construction Site, Millerhill Depot Edinburgh

Works progress on the large scale road and walkway construction of Millerhill Depot for the EGIP Programme, which will implement the electrification of the Edinburgh Glasgow line.